Baltimore Street Access Project to take 18 Months

    Home Uncategorized Baltimore Street Access Project to take 18 Months
    NextPrevious

    Baltimore Street Access Project to take 18 Months

    By developer | Uncategorized | 0 comment | 5 December, 2019 | 0

    Officials see October 2020 as the likely starting point for the beginning phase of the $9.4 million Baltimore Street Access Project.

    CUMBERLAND — Officials see October 2020 as the likely starting point for the beginning phase of the $9.4 million Baltimore Street Access Project.

    Prior estimations had the opening phase possibly beginning in the summer. However, Bobby Smith, city engineer, provided an update on the likely timeline for the project in a Times-News interview on Wednesday.

    Smith said the project should take 18 months with the final touches completed in the spring of 2022. The project calls for the replacement of underground utility lines, followed by reinstalling Baltimore Street and adding streetscape upgrades.

    “I think the earliest realistic time to begin would be October,” said Smith. “If we can start in the fall of next year on the underground work then we can begin working on the streetscape in the following construction season.”

    Smith said the subterranean utility work could continue from October until the ground is likely to freeze by January.

    “In the fall we can still do underground work,” said Smith. “You can get some of the (demolition and digging) done and work on the sanitary sewer and utility lines. You can work to the end of the calendar year as long as the ground hasn’t frozen too much. In January it’s typically frozen.”

    Smith said work would resume in March.

    “We will be shooting for March 1 or April 1 (2021) to begin the construction season,” said Smith. “You still have rain to deal with, but you are not seeing temperatures in the 20s so you can get the contractors out there. That is when you can begin the streetscape work … things you can see.”

    Smith said from March 2021 until the end of the year, much of the installation of Baltimore Street and cosmetic streetscape work will be complete.

    “The main corridor will be done in 2021,” said Smith. “Work will likely continue in 2022. What would be left would be the side (streets) like Liberty and Centre streets.”

    That would peg the total completion of the project in spring 2022. However, Smith said timelines are often subject to change.

    “There are a lot of unknowns. When you start digging you don’t what you find. There is no amount planning that can prepare you for some issues.”

    Smith will be the lead project manager to coordinate the massive project, which includes the Maryland State Highway Administration, EADS Engineering Group, several utility companies, Williams Cochran Design Studio, Cumberland Economic Development Corp., the Downtown Development Corporation and numerous downtown business owners.

    “I will be the project manager,” said Smith. “If we want shovels in the dirt next fall, we need to make sure we are all going down the same path and that comes to our engineering firm (EADS) so they don’t design something we know we can’t afford or there is going to be issues with.

    “If we want the majority done in one construction season, we want to use the contractors’ time most efficiently. You need a chain of command. You don’t want someone going in asking for changes. I don’t want to go through a lengthy review process that could delay giving the engineering firm direction. If there is a deviation, we want it coordinated though one person. If you have large scale changes it has to go back to the SHA for an approval that is a minimum of three months.”

    Paul Kelly, executive director of the CEDC, gave an update on the project’s financial status at a meeting at City Hall on Tuesday. Kelly said he is optimistic an estimated $2.2 million funding gap for the $9.4 million project will be filled in a timely manner. Although the project has been awarded state and federal grants so far, Kelly is seeking to cover the shortage through multiple sources including Gov. Larry Hogan’s capital budget, the Maryland Broadband Cooperative and the state Smart Growth and Community Legacy programs.

    Smith said he would “prefer to have the funding identified knowing the alternative is using city funds. Hopefully that is something we don’t have to do. We don’t want to use (Maryland) bond money for the project.”

    Cumberland Mayor Ray Morriss said he is optimistic.

    “I think the hard work that everyone has done to get us in the position we are right now is to be commended,” said Morriss. “I think it is something that is definitely achievable.

    “So often people truly don’t understand the funding process and how these things work. If we didn’t ask for this funding it would go to Salisbury, Easton, Montgomery County … somewhere else. So we are doing the right thing by bringing it to the city of Cumberland and Allegany County.”

    Follow staff writer Greg Larry on Twitter @GregLarryCTN.

    No tags.

    developer

    More posts by developer

    Related Post

    • Mall Bids Exceed Projections

      By melinda.kelleher@cumberlandmd.gov | 0 comment

      CUMBERLAND, Md. — City officials remain confident they can fill a funding gap of roughly $2 million after reviewing contractor bids Wednesday for the Baltimore Street Access Project. Two bids were submitted for the project,Read more

    • Mall renovation on target for next year

      By melinda.kelleher@cumberlandmd.gov | 0 comment

      CUMBERLAND, Md. — The Cumberland Economic Development Corp. offered updates Tuesday on several key projects including the downtown renovation, Cumberland Gateway and the future of 19 Frederick St. Matt Miller, executive director of the CEDC, conductedRead more

    • CEDC Head says Additional Funds Likely for Downtown Mall Project

      By developer | 0 comment

      CUMBERLAND — Officials say additional funding sources for proposed renovations of the downtown pedestrian mall should materialize over the next 18 months.  Paul Kelly, executive director of the Cumberland Economic Development Corp., gave an update onRead more

    • City to Unveil Design Drawings for Renovated Downtown Mall

      By developer | 0 comment

      City officials will unveil the finished design drawings Tuesday for a newly imagined downtown mall streetscape. CUMBERLAND — City officials will unveil the finished design drawings Tuesday for a newly imagined downtown mall streetscape. TheRead more

    • New Downtown Website In Development

      By developer | 0 comment

      CUMBERLAND — A new website for the city’s downtown district is expected to launch in the spring, Downtown Development Commission Executive Director Melinda Kelleher said Thursday during the group’s virtual meeting. The DDC purchased theRead more

    Leave a Comment

    Cancel reply

    You must be logged in to post a comment.

    NextPrevious

    Recent Posts

    • 11 October, 2022
      0

      Mall Bids Exceed Projections

    • 15 November, 2021
      0

      Mall renovation on target for next year

    • 7 June, 2021
      0

      History of Baltimore Street

    • 21 April, 2021
      0

      CEDC Head says Additional Funds Likely for Downtown Mall Project

    NewsLetter


      Archives

      • October 2022
      • November 2021
      • June 2021
      • April 2021
      • March 2021
      • February 2021
      • January 2021
      • December 2020
      • November 2020
      • September 2020
      • August 2020
      • May 2020
      • January 2020
      • December 2019
      • November 2019
      • August 2019
      • June 2019
      • April 2019
      • March 2019
      • February 2019
      • January 2019
      • November 2018
      • August 2018
      • July 2018
      • May 2018
      • February 2018
      • September 2017
      • January 2017
      • January 2016
      • March 2012

      • Home
      • About
      • FAQ
      • Timeline
      • News & Events
      • BUSINESS LIST
      • Contact

      Subscribe To Newsletter

        © 2021 Reimagine Cumberland | Site by Pikewood Media Group | All Rights Reserved
        • Home
        • About
        • FAQ
        • Timeline
        • News & Events
        • Business List
        • Contact
        Reimagine Cumberland Maryland